The West Campus Paving project is scheduled to begin Tuesday 1/4/11. The Phasing of the project is outlined below. All parking lots will remain open during construction, except for the “Tot Lot” as it needs to be vacant in order to pave. Residents and visitors should move their cars from the “Tot Lot” to the Santa Catalina parking lot by 1/3/11.

Phase 1

Close the Tot Lot

Reconstruct Tot Lot

Reconstruct Perimeter Road from Entrance Rd to South Lot

Maintain access to East Lot at all times. Traffic to East Lot on graded pulverized material for portion of phase.

Duration: 1/4 – 1/25

Phase 2

No parking lot closures

Reconstruct Perimeter Road - from South Lot to West Lot

Duration: 1/26 – 2/8

Phase 3

No parking lot closures

Reconstruct Perimeter Road - from West Lot to North Lot

Duration: 2/9 – 2/23

Phase 4

No parking lot closures

Reconstruct remaining portion of Perimeter Road on north side of complex

Duration: 2/24 – 3/3